Merger and acquisition for gas field production facilities with total investment value $30 million USD. Several analyses are carried out at this project:
Reserve verification
Estimate CAPEX and OPEX
Field development plan review
Commercial and economic evaluation
Verify and ranking the block prospects to upside potentials
There are two cases defined as sensitivity:
Normal dynamic model – 115 mmscfd plateau with the same dynamic model as the 90 mmscfd base case to simulate maximum gas delivery as per gas allocation approval from MEMR.
Optimize dynamic model – 115 mmscfd plateau run with an optimized dynamic model (acknowledging more reservoir connectivity and lower skin, thereby extending the plateau period).